Expansion Update 12/4/2014

The Plattsburgh International Airport expansion is now in phase II. Work that has been completed during the previous period includes:
  • Continued foundation and wall work in the Utility Building area
  • Excavation work in outbound baggage addition area and continued foundation work in this area

Upcoming work will include:

  • The Jet Bridge will temporarily be relocated after New Year's, taking approximately one week to move
  • The outbound baggage shelter will be temporarily relocated after Thanksgiving, taking approximately 10 days. This will not interfere with baggage operations 
There are no airport operational impacts to note during this time. 
 